Fremantle’s new Walyalup Bridge opens three months early after virtual construction planning

The new crossing was coordinated and sequenced digitally, with VR reviews identifying around $300,000 in savings in the first week alone.
PERTH, Australia – November 25, 2026 – Fremantle’s new Walyalup Bridge opened to the public three months ahead of schedule, after the Fremantle Bridges Alliance used digital engineering to work through key construction decisions before they were locked into the build.
The Alliance brought together Laing O’Rourke, Arup, WSP and Main Roads Western Australia. Delivered as part of the Swan River Crossings Project, the new structure is Australia’s first extradosed bridge.
There was little room for error. The bridge sits on a constrained 250-metre footprint, largely along the alignment of the crossing it replaces. It was built alongside the existing structure (which was removed in 2026), next to an operating port and above a river that remained open to boats and ferries.
A late design change or sequencing problem would not stay small for long. So the Alliance set out to settle those questions while they were still manageable.
Working through the build virtually
From day one, the Fremantle Bridges Alliance adopted a planned, governed and value-driven strategy, with Revizto at the centre of its collaborative workflow. 2D drawings, 3D models, permanent works, temporary works and shop drawings came together in one shared space. That gave engineers and construction teams a way to test constructability, examine the detail and understand how one decision could affect what happened next.
Revizto supported model reviews, clash detection, shop drawing checks and RFI markups. Alongside this, 4D staging and sequencing were used to validate methodology and the program, while material quantities were tracked throughout design.
The federated model was then viewed through a VR headset, allowing technical leads and superintendents to test whether planned operations on screen were physically achievable in the field.
Safety was built into that process. Lifting wings, transverse post-tensioning access and temporary blisters were modeled before crews reached those activities, helping reduce working at height and allowing risks to be designed out rather than managed once construction was underway.
“The later a problem appears, the harder and more expensive it becomes to fix. What stands out at Fremantle is how deliberately the Alliance moved that thinking upstream, bringing design, sequencing and site constraints together while there was still time to test different approaches. Opening months early shows what digital engineering can contribute when it becomes part of the construction method itself.”
Arman Gukasyan, Founder and CEO, Revizto
One project, one shared view
For Adam Booth, Project Digital Leader at Laing O’Rourke, the advantage was seeing how decisions connected across the job. That went beyond coordination. By bringing together drawings, models, temporary and permanent works, sequencing and key information, the team could understand the implications before committing people, materials and time.
“Revizto became our single source of truth, giving the team one place to interrogate the bridge in detail before decisions reached site. The virtual walkthroughs helped us identify issues that would otherwise have caused problems and delays much later in the build. What mattered was that VR was not a separate visualization exercise. We were stepping into the model the team was already using to coordinate the work and using it to make real engineering decisions. That is the value of digital delivery for me: understanding more, earlier, so the team can build with greater certainty.”
Adam Booth, Project Digital Leader, Laing O’Rourke
A blueprint beyond Fremantle
What happened at Fremantle matters beyond one crossing. On road, rail and utility programs, a seemingly small change in one location can affect access, sequencing, safety or constructability much further down the route. The longer the asset, the harder those consequences become to see before work begins.
For owners and contractors asking what this approach is worth, Fremantle offers a tangible answer: a landmark piece of Australian infrastructure, delivered in an unforgiving setting, with time returned to the program and costly problems caught before they reached the field.
Building virtually is not about the model itself. It is about arriving on site knowing more about what comes next.
See how the Fremantle Bridges Alliance used Revizto and VR to identify around $300,000 in savings in the first week here.